Hernando Today
|
 
Hernando NewsHernando News

DPW Cleanup Cost Rises $187,000

» 0 Comments | Post a Comment

BROOKSVILLE - The price tag for cleaning up the contaminated former public works compound in downtown Brooksville went up $187,000 Tuesday when county commissioners approved another change order from its consultant.

This was the 10th cost increase request from Creative Environmental Solutions, which has now been paid more than $1.7 million for its work. The last change order was in November 2007.

This latest cost increase will cover the cost of additional soil and water testing at the site at 201 West Martin Luther King Jr. Blvd.

Creative has spent the last several months assessing the scope of the contamination, which the state requires before moving to the remedial stage of the cleanup.

The state set a deadline of Dec. 31 for completion of that site assessment report.

The county met the deadline but determined that more testing was needed.

"Despite a concerted effort by our consultant, the report that we submitted ... indicated that additional sampling and testing is required before site assessment can be considered to be complete," Assistant County Engineer Gregg Sutton said.

Member Agreement / Privacy Statement

Advertisement

Advertisement

Reader Comments

Sort newest to oldest

  1. Results Loading...

Post a Comment (Please Sign In | Register)

  • Keep it clean
  • Respect others
  • Don't hate
  • Don't use web URLs or the comment will not post
  • Don't use language you wouldn't use with your mom
  • Use "Report Inappropriate Content" link when necessary
  • See Member Agreement for details
Please sign in to respond | Sign In | Register

Deal of the Day

Advertisement

Advertisement

Weather Alerts:
Email
Cell Phone

Advertisement

Media General
DealTaker.com - Coupons and Deals
black Friday 2010 ads
KewlBoxBoxerJam: Games & Puzzles
Games, Puzzles & Trivia
Blockdot: Advergaming and Branded Media
Advergaming and Branded Media

MyYahoo!